Thorpe PV Case Study
Midland Rock successfully navigated tight deadlines, challenging site conditions, and regulatory hurdles to deliver critical enabling works for the Thorpe PV solar farm. Through strategic planning, rapid mobilisation, and expert earthworks, we prepared 1km of road and multiple compounds despite wet weather and site complexities—setting the foundation for seamless solar construction and long-term renewable energy success.
THORPE PV SOLAR PROJECT
Midland Rock was engaged to deliver comprehensive enabling works for the Thorpe PV solar farm construction project. The scope encompassed 1km of road construction, site preparation across four compounds, vegetation clearance, cut and fill operations, and Section 278 highway works to secure site access and facilitate solar farm construction and ongoing maintenance operations.

Value
£500K+
Programme
4 Weeks
Services
Compound And Internal Road Construction
The Challenge
The Thorpe PV project presented several interconnected challenges that required strategic planning and rapid mobilisation:
Tight Construction Timeline – The client imposed a strict deadline to complete all enabling works before solar farm construction commenced immediately thereafter. This compressed schedule left no room for delays or rework, demanding efficient coordination and material management throughout the project duration.
Challenging Site Conditions – The site comprised overgrown agricultural fields requiring complete vegetation clearance before construction could begin. Significant topographical variations necessitated cut and fill operations to reduce gradients and create level surfaces suitable for compound storage areas and solar panel installation.
Weather Constraints – Works progressed into the wet weather season, with unpredictable rainfall threatening ground conditions, site access, and construction productivity. Poor ground conditions increased the complexity of maintaining safe working surfaces and protecting materials from water damage.
Regulatory Requirements – Planning permission remained pending during the early project phases, whilst Section 278 highway works were required to gain formal access to the site. These regulatory dependencies created uncertainty regarding site access and scheduling flexibility.
Material and Equipment Logistics – Delivering and positioning substantial quantities of materials and plant on challenging terrain whilst managing multiple work activities (vegetation clearance, earthworks, road construction, and compound development) simultaneously required careful coordination and strategic placement to support sequential solar construction phases.
The Solution
Midland Rock deployed a comprehensive, strategically planned approach to overcome these challenges:
Rapid Site Mobilisation – Recognising the time-critical nature of the project, Midland Rock gained immediate access via existing farm access routes and quickly mobilised specialist plant and materials to site. This swift response established an operational base before weather conditions deteriorated further.
Vegetation Management – A dedicated vegetation clearance operation ensured the site was properly prepared, removing overgrown growth and creating workable surfaces for subsequent earthworks and construction activities.
Strategic Earthworks – Cut and fill operations were carefully planned and sequenced to reduce site gradients, level compound areas, and create optimal conditions for both temporary storage and solar panel installation. Midland Rock’s experienced earthmoving teams executed these operations with precision, managing material placement to support subsequent construction phases.
Material and Plant Positioning – Strategic placement of materials, aggregates, and plant equipment was coordinated to create a seamless workflow for the follow-on solar construction work. This forward-thinking approach minimised material double-handling, reduced site congestion, and ensured resources were positioned exactly where solar contractors needed them.
Flexible Project Management – Despite adverse weather and regulatory uncertainties, Midland Rock maintained programme momentum through adaptive planning and resource management. The team prioritised critical path activities, adjusted daily schedules based on ground and weather conditions, and maintained open communication with the client and follow-on contractors.
Quality Control – Throughout the project, strict quality standards were maintained to ensure all enabling works met the precise specifications required for solar farm construction and long-term operational efficiency.
Project Outcome
Midland Rock successfully delivered all enabling works ahead of the compressed schedule, creating a fully prepared site ready for immediate solar farm construction. The strategic approach to material management, vegetation clearance, and earthworks ensured seamless handover to the solar construction team, with no delays or rework required. Despite challenging weather, regulatory constraints, and tight timescales, the project was completed on programme, demonstrating Midland Rock’s capability to manage complex, time-critical infrastructure projects with precision and flexibility.
This project exemplifies Midland Rock’s commitment to delivering results under challenging conditions—supporting the UK’s renewable energy infrastructure whilst maintaining the highest standards of safety, quality, and professionalism.
Our Services
We offer a wide range of services designed to meet the diverse needs of the construction and civil engineering industries:
Our Accreditations
Similar project in mind?
We are always open to discussing new opportunities and projects within the Midlands or further afield. Our team is here to provide expert guidance and high-quality services tailored to your specific needs. For more information about our services or to discuss your project requirements, please contact us today.